Carroll Middle Campus

Building History of the Carroll Middle campus, starting with the PLAN 2000 improvements and moving backwards:

PLAN 2000 Projects

Description Year Completed
Asphalt repair for front driveway. Scheduled July 2003
Replace asphalt track. Scheduled July 2003

Pre-PLAN 2000 Projects

Description Year Completed
Media center expansion/renovation 1993
Classroom/Auditorium addition 1997
Re-roofing, ADA, security system, A/C kitchen 2000
Provide grease trap for kitchen 2001
ADA, stairwell code upgrades 2001