37 Re-roofing Projects |
|||
. |
School Name |
Construction Date |
Total Project Cost |
| 1 |
APEX ELEMENTARY | 2004 |
$77,000.00
|
| 2 |
APEX HIGH | 2004 |
$450,000.00
|
| 3 |
AVERSBORO ELEMENTARY | 2005 |
$298,000.00
|
| 4 |
BAUCOM ELEMENTARY | 2007 |
$62,500.00
|
| 5 |
BRIARCLIFF ELEMENTARY | 2007 |
$62,500.00
|
| 6 |
BROOKS ELEMENTARY | 2007 |
$62,500.00
|
| 7 |
BROUGHTON HIGH | 2004 |
$168,700.00
|
| 8 |
BUGG ELEMENTARY | 2006 |
$45,000.00
|
| 9 |
CARNAGE MIDDLE | 2005 |
$89,000.00
|
| 10 |
SERVICE CENTER |
2004 |
$317,000.00
|
| 11 |
COMBS ELEMENTARY | 2007 |
$62,500.00
|
| 12 |
CONN ELEMENTARY | 2004 |
$86,100.00
|
| 13 |
EAST GARNER MIDDLE | 2007 |
$549,000.00
|
| 14 |
EAST WAKE HIGH | 2005 |
$93,000.00
|
| 15 |
FUQUAY VARINA MIDDLE | 2006 |
$247,500.00
|
| 16 |
FUQUAY VARINA HIGH | 2006 |
$26,400.00
|
| 17 |
GREEN ELEMENTARY | 2004 |
$94,200.00
|
| 2006 |
$62,500.00 |
||
| 18 |
HODGE ROAD ELEMENTARY | 2004 |
$635,600.00
|
| 19 |
HUNTER ELEMENTARY | 2004 |
$113,300.00
|
| 20 |
JOYNER ELEMENTARY | 2006 |
$62,500.00
|
| 21 |
LACY ELEMENTARY | 2006 |
$62,500.00
|
| 22 |
LEESVILLE ELEMENTARY | 2004 |
$489,700.00
|
| 23 |
LEESVILLE MIDDLE | 2005 |
$892,000.00
|
| 24 |
LEESVILLE HIGH | 2006 |
$1,536,900.00
|
| 25 |
LOCKHART ELEMENTARY | 2004 |
$222,000.00
|
| 26 |
MILLBROOK ELEMENTARY | 2005 |
$342,000.00
|
| 27 |
MT. VERNON SPECIAL/OPTIONAL | 2005 |
$54,300.00
|
| 28 |
PARTNERSHIP SPECIAL/OPTIONAL | 2006 |
$87,800.00
|
| 29 |
POE ELEMENTARY | 2006 |
$62,500.00
|
| 30 |
POWELL ELEMENTARY | 2005 |
$420,800.00
|
| 31 |
ROOT ELEMENTARY | 2007 |
$62,500.00
|
| 32 |
SANDERSON HIGH | 2004 |
$354,200.00
|
| 33 |
SMITH ELEMENTARY | 2006 |
$263,700.00
|
| 34 |
VANDORA SPRINGS ELEMENTARY | 2007 |
$62,500.00
|
| 35 |
WEST CARY MIDDLE | 2006 |
$130,700.00
|
| 36 |
WAKE FOREST MIDDLE | 2005 |
$1,274,000.00
|
| 37 |
WILEY ELEMENTARY | 2005 |
$100,400.00
|
|
|
TOTAL | $10,083,300.00
|
|