PLAN 2004: Repair Projects - Table

PLAN 2004: Repair Projects - Table



PLAN 2004 SCHOOL BUILDING PROGRAM (2004-2008)
52 Repair Projects
PROJECT NUMBER
SCHOOL NAME
SCOPE OF WORK
TOTAL PROJECT COST
1
Apex High Sandblast and paint structural steel in stadium-$40K / New Serving Line
$103,373
2
Aversboro Elementary Floors throughout
$271,638
3
Brassfield Elementary Carpet and HVAC like Rand Rd except include Cooling Tower and heat exchanger
$1,113,531
4
Brentwood Elementary Rpl Boiler
$112,035
5
Brooks Elementary Rpl outdoor condensing unit serving multi-purpose room-$40K/ Rpl carpet multi-purpose room-$30K
$75,804
6
Broughton High Rpl cooler and freezer. Replace two 180 ton chillers
$312,357
7
Bugg Elementary Rpr driveway, restripe pkg lot-$35K
$38,196
8
Carnage Middle Floor and Ceiling in areas not addressed in last renovation
$116,939
9
Conn Elementary Rpl boilers
$130,184
10
Creech Rd. Elementary Rpl Cooling Tower and Pumps
$176,506
11
East Millbrook Middle Correct drainage-$25K / Rpl flooring throughout except admin or Bldg 1. New Cooler & Freezer
$326,919
12
East Wake High Replace flooring in misc. areas / New Serving Lines
$217,628
13
East Wake Middle Flooring throughout / New water and sewer service including generator and well house. New Serving Line
$1,227,817
14
Fox Road Elementary Carpet and HVAC like Rand Rd except include Cooling Tower and heat exchanger
$1,113,531
15
Fuquay Elementary Flooring throughout. New Serving Line. Water and sewer improvements including generator, auto dialer and transfer switch.
$332,394
16
Fuquay High Pave back parking lot, new bus storage lot and resurface existing paved lots. Sandblast and paint structural steel in stadium. Flooring throughout except new additions. New Serving Line
$477,875
17
Garner High Ventilate mech room in kitchen for step down transformer, rpl AHU (4-6) units located in center of old main bldg. Fix air flow problems. Rpl fan coil units in kitchen. Flooring in classrooms. New Serving Line. Water and sewer improvements including generator, auto dialer and transfer switch.
$496,754
18
Green Elementary Flooring multi-purpose room and classrooms
$272,035
19
Knightdale Elementary Rpl cooler and freezer.
$30,123
20
Lacy Elementary HVAC Renovations and finishes in media center, computer classroom and Kitchen / Condensing Unit in Multi-Purpose Room / Lower mechanical equipment
$807,195
21
Lead Mine Elementary Carpet and HVAC like Rand Rd except include Cooling Tower and heat exchanger
$1,113,531
22
Leesville Elementary Flooring throughout
$291,730
23
Lincoln Heights Elementary Flooring throughout. New Serving Line
$219,734
24
Lockhart Elementary Flooring throughout except additions
$197,772
25
Northridge Elementary New Serving Line
$24,133
26
Oak Grove Elementary Flooring throughout
$291,730
27
Parent Volunteer Program Funding for Matching Grant Program
$453,074
28
Penny Rd Elementary Carpet and HVAC like Rand Rd except include Cooling Tower and heat exchanger. New Serving Line
$1,135,801
29
Pleasant Union Elementary Rpl cooling tower and heat exchanger. Provide centrifugal separator and pumps, Rpl carpet throughout.
$530,910
30
Poe Elementary Rpl flooring in mult-purpose room and other misc areas. Rpl heat pumps serving multi-purpose rm bldg.
$130,184
31
Reedy Creek Elementary Water and sewer improvements including generator, auto dialer and transfer switch.
$42,776
32
Root Elementary Correct drainage with retaining wall-$750K / Rpl condensing unit for multipurpose room- $40K / Overlay Asphalt-$70K. New Serving Line
$954,410
33
Sanderson High Provide ventilation air to East Building
$288,884
34
Smith Elementary New Walk-In Cooler & Freezer
$30,123
35
Stough Elementary Uprgrade restrooms and flooring left out of previous renovations
$560,107
36
Swift Creek Elementary Water and sewer improvements including generator, auto dialer and transfer switch.
$42,776
37
Vance Elementary Rpl Cooling Tower and Pumps. Repipe Mechanical Room. Rpl Carpet Throughout. New Serving Line. Water & Sewer improvements including generator, auto dialer and transfer switch.
$595,095
38
andora Springs Elementary Resurface basketball courts-$10K. Rpl rooftop units for media center and install BAS controls.
$162,730
39
Various Schools ADA Needs from Carter Burgess Survey
$2,265,372
40
Various Schools ADA Playground Surfacing @ 50 Schools
$2,265,372
41
Wake Forest High Rpr drive-$70K / Rpl cooling tower.
$297,168
42
Wake Forest Middle Rpl cooling tower / New Walk-In Cooler & Freezer
$199,488
43
Wakefield High Water & sewer improvements including generator, auto dialer, & transfer switch
$41,307
44
Wendell Elementary Rpl boiler and cooling tower. New Serving Line
$274,946
45
West Cary Middle Rpl Flooring throughout except 1996 Bldg
$281,710
46
West Millbrook Middle Correct drainage / Rpl ashpalt / Rpl carpet
$707,528
47
Wilburn Elementary Flooring throughout except 8 classrooms and multi-purpose room
$169,026
48
Willow Springs Elementary Water & sewer improvements including generator, auto dialer, & transfer switch
$42,776
49
Yates Mill Elementary Water & sewer improvements including generator, auto dialer, & transfer switch
$41,307
50
York Elementary Rpl main boiler
$112,345
51
Zebulon Elementary Rpl Carpet throughout. New Serving Line
$304,247
52
Zebulon Middle Asphalt track-$75,000. Flooring throughout except new addition
$338,068
  TOTAL   $22,158,993