PLAN 2004: New Schools - Table

PLAN 2004: New Schools - Table



PLAN 2004 SCHOOL BUILDING PROGRAM (2004-2008)
13 New Schools and 1 Pre-kindergarten Center
School Number
New School
Completion Date
Total Cost
1
High H4 - Panther Creek
2006
$40,668,873
2
High H5 - Holly Springs
2006
$40,571,722
3
Elementary E9
2006
$12,952,658
4
Elementary E10
2006
$14,516,821
5
Elementary E12
2007
$15,033,140
6
Elementary E11
2006/2007
$13,433,884
7
Elementary E16 - Brier Creek Area Site
2007
$12,948,563
8
Elementary E14
2007/2008
$13,890,416
9
Elementary E17
2008
$15,582,912
10
Elementary E13
2007
$15,033,140
11
Elementary E18 - Holly Springs Area Site
2007
$15,033,140
12
Elementary E19
2008
$13,890,416
13
Elementary E15
2007
$15,033,140
14
Pre-Kindergarten Special Programs Facility
2007
$2,500,000
.
*TOTAL  
*$241,088,825
* Plus funding for phase 1 of 2 for the new Wendell Middle School and phase 1 of 2 for the new Heritage High.