View of the interior Link Building completed renovations.
|
|
Project Budget |
| Design |
$1,068,375 |
$1,068,375 |
$830,100 |
$1,068,375 |
| Construction |
$22,650,483 |
$22,650,483 |
$22,298,055 |
$22,650,483 |
| Misc. Contracts |
$1,067,071 |
$1,067,071 |
$390,030 |
$1,067,071 |
| Furn/Equip. |
$230,155 |
$230,155 |
$48,668 |
$230,155 |
| Library Books |
$81,154 |
$81,154 |
$0 |
$81,154 |
| Savings |
$0 |
$0 |
$0 |
$0 |
Financial Commitments as of
3/31/09
*$2,240,672 from Plan 2004 is being used to fund part of this CIP 2006 project
|
|
| Program Summary |
|
Major renovations to include general classrooms, staff spaces, administration, and student support services.
|
|
| Progress Status |
|
Phase IIA: Completed.
Phase IIB: This last phase of construction consists of renovations to the 1976 Building (sometimes called the Link Building) and the Dining Room/Kitchen area. Students and Staff have now occupied the new Kitchen and Dining Room areas.
Renovation of the Link Building is now 96% complete. Some work remains with some finishes as well as landscaping and painting of the exterior building.We expect to have this renovation completed in June 2009.
|
|
| Total Acres |
70.46 |
| Gross Building SF Prior to this Project |
265,083 |
| Demolished Square Feet |
(19,641) |
| New Square Feet |
55,058 |
| Renovated Square Feet |
78,759 |
|
| Plan 2004 |
$2,365,672 |
| CIP 2006 |
$22,428,769 |
| CIP 2006 Offsite |
$302,797 |
|
| Start Design |
10/23/06 |
| Schematic Design |
2/22/07 |
| Construction Docs |
2/06/07 |
| Bid |
4/24/07 |
| Notice to Proceed |
5/22/07 |
| Anticipated Occupancy |
August 2009 |
|
|