The new greenhouse has been installed.
|
|
Project Budget |
| Design |
$1,068,375 |
$1,068,375 |
$830,100 |
$1,068,375 |
| Construction |
$22,650,483 |
$22,650,483 |
$22,186,209 |
$22,650,483 |
| Misc. Contracts |
$1,067,071 |
$1,067,071 |
$324,860 |
$1,067,071 |
| Furn/Equip. |
$230,155 |
$311,309 |
$22,000 |
$230,155 |
| Library Books |
$81,154 |
$0 |
$0 |
$81,154 |
| Savings |
$0 |
$0 |
$0 |
$0 |
Financial Commitments as of 6/30/08
*$2,240,672 from the Plan 2004 is being used to fund part of CIP 2006 project
|
|
| Program Summary |
|
Major renovations to include general classrooms, staff spaces, administration, and student support services.
|
|
| Progress Status |
|
Phase IIA: A new greenhouse has now been installed and the first lift of asphalt in the new student parking lot has been completed. Carpet, marker boards and other finishes are being installed in the new two story classroom building. Interior painting is nearly completed. Overhead inspections have been completed.
Phase IIB: Will consist of renovations to the 1976 Building and Media Center. Sprinkler work in the Media center was completed and the space has been returned to the school. Installation of roofing membrane and exterior curtain wall and glass on the connector walkway between the new classroom building and the existing Auxiliary Gym is nearly completed. Air handler units have been installed. Sheetrock is currently being installed.
|
|
| Total Acres |
70.46 |
| Gross Building SF Prior to this Project |
265,083 |
| Demolished Square Feet |
(19,641) |
| New Square Feet |
55,058 |
| Renovated Square Feet |
78,759 |
|
| Plan 2004 |
$2,365,672 |
| CIP 2006 |
$22,428,769 |
| CIP 2006 Offsite |
$302,797 |
|
| Start Design |
10/23/06 |
| Schematic Design |
2/22/07 |
| Construction Docs |
2/06/07 |
| Bid |
4/24/07 |
| Notice to Proceed |
5/22/07 |
| Anticipated Occupancy |
August 2009 |
|
|