View Slide Show
|
|
Project Budget |
| Design |
$898,579 |
$898,579 |
$820,322 |
$898,579 |
| Construction |
$17,930,912 |
$17,930,912 |
$17,564,168 |
$17,600,000 |
| Misc. Contracts |
$481,441 |
$481,441 |
$248,267 |
$481,441 |
| Furn/Equip. |
$2,235,320 |
$2,235,320 |
$985,086 |
$2,235,320 |
| Library Books |
$326,804 |
$326,804 |
$1,406 |
$326,804 |
| Savings |
$1,052,585 |
$1,052,585 |
$0 |
$1,052,585 |
Financial Commitments as of
3/31/09
|
|
| Program Summary |
|
First re-use of the E-22 Elementary (Mills Park Elementary) prototype on a site west of Wendell.The main floor of the school will satisfy all the needs of K-1 students with K-1 classrooms, 2 self contained classrooms (self contained suite), 1 CCR, 1 general support and all support facilities. The second floor is to accommodate 2nd & 3rd grade classrooms, and third floor to accommodate 4th & 5th grade classrooms.
|
|
| Progress Status |
|
Lake Myra received a Temporary Certificate of Occupancy on May 1, 2009. The building is approved for Staff members only. By June 1, 2009, the furniture and equipment will begin to be set in place and the staff will begin to move-in.
Picture Taken: 5/15/09
|
|
| Total Acres |
16.8 |
| Gross Building SF Prior to this Project |
0 |
| Demolished Square Feet |
( 0 ) |
| New Square Feet |
103,769 |
| Renovated Square Feet |
0 |
|
| CIP 2006 |
$22,746,541 |
| Wake County Parks & Recreation |
$95,150 |
| Town of Wendell |
$83,950 |
| Land Purchase |
$672,000 |
|
| Start Design |
2/1/07 |
| Schematic Design |
7/16/07 |
| Construction Docs |
12/11/07 |
| Bid |
1/29/08 |
| Notice to Proceed |
3/10/08 |
| Anticipated Occupancy |
July 2009 |
|
|