View Slide Show
|
|
Project Budget |
| Design |
$887,379 |
$887,379 |
$820,322 |
$887,379 |
| Construction |
$17,954,826 |
$17,954,826 |
$17,416,669 |
$17,954,826 |
| Misc. Contracts |
$476,441 |
$476,441 |
$145,678 |
$476,441 |
| Furn/Equip. |
$2,227,606 |
$2,227,606 |
$1,138 |
$2,227,606 |
| Library Books |
$326,804 |
$326,804 |
$0 |
$326,804 |
| Savings |
$0 |
$0 |
$0 |
$0 |
Financial Commitments as of 6/30/08
|
|
| Program Summary |
|
First re-use of the E-22 Elementary (Mills Park Elementary) prototype on a site west of Wendell.The main floor of the school will satisfy all the needs of K-1 students with K-1 classrooms, 2 self contained classrooms (self contained suite), 1 CCR, 1 general support and all support facilities. The second floor is to accommodate 2nd & 3rd grade classrooms, and third floor to accommodate 4th & 5th grade classrooms.
|
|
| Progress Status |
|
Site work began on this project in mid-March 2008, with the installation of erosion control and tree protection measures. The majority of the building steel and roof decking has now been erected, and the floor slabs have been placed. Exterior and interior masonry work is currently in progress. Mechanical systems are being installed, including HVAC equipment and associated ductwork.
Picture Taken: 8/18/08
|
|
| Total Acres |
16.8 |
| Gross Building SF Prior to this Project |
0 |
| Demolished Square Feet |
( 0 ) |
| New Square Feet |
103,769 |
| Renovated Square Feet |
0 |
|
| CIP 2006 |
$21,693,956 |
| Wake County Parks & Recreation |
$95,150 |
| Town of Wendell |
$83,950 |
| Land Purchase |
$672,000 |
|
| Start Design |
2/1/07 |
| Schematic Design |
7/16/07 |
| Construction Docs |
12/11/07 |
| Bid |
1/29/08 |
| Notice to Proceed |
3/10/08 |
| Anticipated Occupancy |
July 2009 |
|
|