ROOT ELEMENTARY
3202 Northampton Road
Raleigh, NC 27609 Map it
PLAN: CIP 2006

Get Directions Close Window

Root Elementary

Project Budget
ItemCurrent BudgetBudget AvailableCommittedTotal Projected
Design$1,081,664$1,081,664$1,020,035$1,050,000
Construction$16,068,005$16,068,005$15,189,017$15,250,000
Misc. Contracts$2,673,154$2,673,154$2,414,987$2,673,154
Furn / Equip$1,065,812$1,065,812$755,131$1,065,812
Library Books$50,252$50,252$0$50,252
Savings$0$0$0$0

Financial Commitments as of 9/31/2009

Financial Commitments as of 9/31/2009

Program Summary

Master plan campus. Demolish Building A (1958,1966) and a section of building B (1958). Construct new classrooms, student support services, administration, cafeteria/multi-purpose room, and support spaces. Renovate existing multipurpose building for classrooms. Renovate all areas that are not demolished. Address site circulation and ADA accessibility. Upgrade play fields.


Progress Status

The final move from the modular campus is underway, with school starting at the new facility at the beginning of November. The project is now in the warranty and close-out phase.



Picture Taken: 8/17/2009


Dimensions
Total Acres 7.52
Gross Building SF Prior to this Project 47,885
Demolished Square Feet
( 33,752 )
New Square Feet 62,268
Renovated Square Feet 14,137
Grand Gross Building SF Total 76,401
Source of Funding
CIP 2006$20,638,887
Plan 2004$300,000
Total Funds$20,938,887
Milestones
Start Design 2/06/2007
Schematic Design 2/15/2007
Construction Docs 10/02/2007
Bid 3/20/2008
Notice to Proceed 6/13/2008
Anticipated Occupancy October 2009