PLAN 2000 Mid-Program Update

October 2002

Summary

14 New Schools

$239.0 M

Existing School Improvements
64+ systemwide and 32 school-specific

$284.1 M

Program Contingency

$5.5 M

Advance Funding
for land purchases & planning for future schools

$21.4 M

Total

$550.0 M

 

 

PLAN 2000 is funded with $500 million in bonds and $50 million in general revenues, called "pay-as-you-go" revenues, from the Wake County government.

 

14 New Schools

 

2002

2003

2004

1 Special/Optional

0

0

1

8 Elementary

3

1

4

4 Middle

2

1

1

1 High

0

0

1

Total

5

2

7

 

 

 

 

Dates reflect the year schools will be complete. Some will serve as "swing space" - meaning they will house students from other schools during major renovations before opening with their own students.

 

PLAN 2000 New Schools

Central & Northern Wake
Raleigh, Rolesville, Wake Forest

Southeastern Wake
Garner, Knightdale, Wendell, Zebulon

Southwestern Wake
Apex, Cary, Fuquay-Varina, Holly Springs, Morrisville

     

Heritage Elementary

Forestville Road Elementary

Ballentine Elementary

Heritage Middle

Knightdale High

Carpenter Elementary

Special/Optional Middle

 

Cedar Fork Elementary

 

 

Highcroft Drive Elementary

 

 

Holly Ridge Elementary

 

 

Turner Creek Elementary

 

 

Holly Ridge Middle

 

 

Reedy Creek Middle

 

 

Salem Middle